The Town of Cobourg and Lakefront Utility Services Inc. have engaged CIMA Canada Inc. to complete the design of the reconstruction of King Street West from Burnham Street to William Street.
The focus of this project is to replace the watermain, sanitary sewer and storm sewer as well as replacing the concrete sidewalk, road curbs and asphalt pavement. Water and sanitary sewer services will be replaced to the property line and connected to existing service pipes. There is no cost to the homeowner for this work. The project will include minor repairs to the King Street West / Cobourg Creek bridge and the construction of a new re-aligned entrance to Wastewater Pollution Control Plant #1.
The project will also include the construction of a 2.5m wide concrete multi-use path on the south side of King Street West, replacing the existing 1.2m wide concrete sidewalk. This will provide an off-road travel area for both cyclists and pedestrians separated from vehicular traffic.
The Town of Cobourg, Lakefront Utility Services Inc. and CIMA Canada Inc. hosted a Public Information Centre (PIC) for this project on September 17, 2024 at the Cobourg Community Centre. The PIC provided the opportunity for the Town and LUSI to share information about the project, hear concerns from the public, and receive valuable feedback.
The design for the project is currently underway and construction is planned to start in spring of 2025, pending budget approvals.
Meeting presentation material is available on the Plans, Reports and Studies page of the Town of Cobourg website.
For further information on to submit comments on the project, please contact either of the following individuals:
Terry Hoekstra, C.E.T., LET, rcca, Larry Spyrka
Deputy Director, Engineering Manager of Water Capital Projects
Town of Cobourg Lakefront Utility Services Inc.
740 Division Street, Building 7 207 Division Street
Cobourg, ON K9A 0H6 Cobourg, ON K9A 4L3
905-372-9971 ext. 4371 905-372-2193 ext.5238
thoekstra@cobourg.ca lspyrka@lusi.on.ca